Construction preparation of aluminum honeycomb panel
1. Personnel preparation: 2 installers, 2 porters and 1 welder.
2. Tool preparation: 1 electric hammer, 1 hammer, 2 adjustable and fixed wrenches, 1 2m guiding rule, 1 plumb bob, 2 angle rulers, 1 wire brush, 2 electric hand drills, 2 forceps, 2 "+" screwdrivers, 1 glue gun, 1 ash knife, 1 tape measure, 2 red and blue pencils, 1 electric welding machine and 1 level ruler.
Setting out of stone material aluminum honeycomb plate construction
1. The perpendicularity of the structural column is correct. Hang the vertical line on the axis of the keel installation position, measure each point up and down with the angle ruler, record the data, and enlarge the average value by 10 mm.
2. Mark the axis position on the floor with a red and blue pencil, draw it out with a 90 ° angle ruler extension lead, and determine the keel axis of the relative position, with the correct error as above.